Difference betn restore & updating baseline in P6

Richu RoseMember for 19 years 8 months
Created
5
5
0
Hi Planners,

What is the difference between restore baseline & update baseline.

Richu

5 replies

Oldest first
  1. 0
    David Forrest ·
    Restore baseline detatches the baseline from the project and restores it as a project. Update baseline updates any changes that have been made to the main project into the selected baseline.
  2. 0
    James Soto ·

    How can I update the %

    How can I update the % complete from 0% to 100 %?

  3. 0
    James Soto ·

    Can you help me? I need to

    Can you help me? I need to update from 0% to 100 %.

  4. 0
    Gary Whitehead ·

    Select the activity Select

    Select the activity

    Select the "Status" tab

    tick the "Started" box

    choose the correct "started" date

    tick the "finished" box

    choose the correct "finished" date

  5. 0
    Khuong Do ·

    Hi, You can understand the

    Hi, You can understand the difference by reading this post https://doduykhuong.com/2016/09/06/how-to-update-baseline-in-primavera-p6/

Log in or join to reply