how can i plot more than one resource histogram in a single graph???

5 replies

Oldest first
  1. 0
    Naveen Subbaiah ·
    Ahmed,

    You cannot plot more than one resource histogram in a single graph. However, the cumulative histogram of more than one resource can be plotted by having them segregated through some resource codes.

    Regards
    Naveen
  2. 0
    Mimoune Djouallah ·
    naveen,thanks really for this answear, i tried everything without success, in p3 i used to plot many ressources filtred by cost account ( useful for cashflow report) but with p6 no way to do that, or am i missing something ?
  3. 0
    Arnold Puy ·
    Ahmed,

    I am not sure if this is what you need. You can try this.

    1. Go to Resource Usage Profile
    2. Right click on the open space at your right bottom.
    3. Tick Stacked Histogram
    4. Right click & select Resource Usage Profile Option.
    5. Tick ADD -> Filters -> where Resource ID equals "Value"

    Note:
    You cannot combine Resource Type. e.g.
    (Labor only, Nonlabor only or Material Only).

    Hope this can help you.


    Arnold
  4. 0
    Ahmed Safwat ·
    THE METHOD YOU SAID FOR PLOTTING RESOURCES WHICH YOU SELECT IN ONE GRAPH IN ONE HISTOGRAM.
    THE PROBLEM IS HOW TO PLOT MULTIPLE RESOURCES IN MULTIPLE HISTOGRAMS SEPARATELY IN ONE GRAPH .
  5. 0
    Santosh Bhat ·
    You’re talking about a feature that existed in P3.1 under graphical reporting.

    It is no longer available in P5/P6