Skip to content

P6 Baseline Total % not appear when summerize

Kamarul Bahrin HassanMember for 21 years 2 months
Created
11
3
0
Dear all P6 expert,


anybody can help me, why total summary % for BASELINE not appear when i summarise or any total % for baseline not appear, I already updated my baseline. only appear Total % for current project only. I cant compare with baseline %. anyone can help me.

Thank you,

KB

11 replies

Oldest first
  1. 0
    Arnold Puy ·
    Hi Kamarul,

    Is your programme cost-loaded? If not, try to allocate the cost to your baseline as well as your current schedule.

    Regards,

    Arnold
  2. 0
    Kamarul Bahrin Hassan ·
    Dear Arnold,

    My program is cost loaded. all the total percentage for current appear but for the total baseline not appear when i summarized. I can’t find the error why.
  3. 0
    Arnold Puy ·
    Hi Kamarul,

    What Total %age do you mean? If your baseline schedule is cost-loaded, try to add one column the "Schedule % Complete".

    Regards,

    Arnold
  4. 0
    Kamarul Bahrin Hassan ·
    HI arnold,

    What i mean is the column for Baseline % (Total Baseline % column ) when i summarise. the total % not show anything.

    tq
  5. 0
    Arnold Puy ·
    Hi Kamarul,

    Let me clear something, there is no (Total Baseline %). For baseline you can show "Schedule % Complete" when you are trying to compare against current (Performance % Complete).

    When you are talking about summary, is this the Summary Band in the WBS Level 1?

    Not showing anything, you mean it is "BLANK or ZERO"?

    Regards,

    Arnold
  6. 0
    Kamarul Bahrin Hassan ·
    Dear Arnold,


    Yes no showing anything "Blank".. all BASELINE etc: BL % duration % complete or BL1 if i attached another Baseline. All the total percentage didn’t show anything " Blank" when summarized.

    Tq
  7. 0
    Arnold Puy ·
    Hi Kamarul,

    Yes you are right. BL % Complete for (Activity, Duration, Costs & Units) does not roll-up in the summary band only Schedule % Complete.

    Regards,

    Arnold
  8. 0
    Kamarul Bahrin Hassan ·
    Dear Arnold,

    Do you have any solution for this problem.? P6 software problem...

    tq
  9. 0
    Maghsoud Joudi ·
    use "performance progress%".
    but to be carefull about unit cost in Base line and current plans. it will affect the summary% and also current%!!!
  10. 0
    D Artagnan ·

    This is also my problem. I

    This is also my problem. I have tried almost all the options but still in vain.

  11. 0
    Ayman Eleish ·

    Dear Kamarul, You are

    Dear Kamarul,

    You are completely right,in P6 you can not show the summarization of the Baseline,and that was acknowledged by the company themselves.

    Realy it is very bad for all planners.

    If you are compeled to do the same ,it can be done by using the user defined showing the progress on a summary bar for base line,but it is not in my mind at the time being ,you can search for it at the net.

    Ayman

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?