Calc Costs from Units feature v6.1

John HartmanMember for 21 years 2 months
Created
1
2
0
Can anyone let me know if this feature can be applied to remaining units only? It appears it’s used in conjunction with the auto compute actuals tag.

What I’m trying to do is import actual hours/cost and have the remaining cost calculated by the remaining units (hours). But it seems to overwrite the total cost (incl actual cost) when I modify the remaining units.

1 reply

Oldest first
  1. 0
    John Hartman ·
    Found the answer in Prim24687 (no).

    As a workaround, they suggest creating UDFs to store the cost/units you want to keep static. Curious if anyone has done this?