Skip to content

P3e version 5- Baseline problems

Norul Faezah NohiMember for 18 years 3 months
Created
4
4
0
Hi all,

I have problems with P3e baselines.Whenever I tried to copy a file which was baselined to a new one, the old previous baseline didnt copy as I thought it should be.Instead, the baseline bar in the new file shifted follows the progress bar even though I have not re-schedule it yet i.e. both the data dates are still the same.What I did just copy the first file to a new file. Looking for any P3e experts to help me or provide /share problems/answers why this happens.
.thanks.
Norul











4 replies

Oldest first
  1. 0
    Dieter Wambach ·
    Norul
    This is solved in P6. In P5, baselines were not copied together with a project.
    You have to ways: Upgrade to P6 or unlink ("Restore") the BL --> Copy project + BL --> create BL again out of this BL-project.
    Regards
    Dieter
  2. 0
    Prem Kumar, ·
    but why exporting baseline is not copied along with the project even in P6
  3. 0
    Dieter Wambach ·
    Prem
    This item is solved in P6, so you can copy BLs together with the project. During the call for copy there is a screen where you can select those BL to copy and those for not.
    Dieter
  4. 0
    Norul Faezah Nohi ·
    Dieter Wambach,

    Thanks for the reply :). I will try to propose this to my company to use P6 if possible. At the moment , I always encountered this baseline problems/inconsistencies everytime!

    **Norul**

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?