Schedule & Perforemanc % Complete Roll up
In the Open Standard
Riyadh YahiaMember for 18 years 2 months
- Created
- 19
- 5
0
Hi To ALL,
I have a Project scheduled on P6, I made WBS for Shopdrawing, Material sbumittal & Approval and Construction.
Then I add resourcs manpower to Construction (WBS) only.
when I start updating i noticed that Scheduled and Performance % complete roll up are showen for Construction (WBS) but for shopdrawing and material (WBS) remain Zero.
I tried to add Labor resource to S.D & M. (wbs) but still the problem is the same.
Can Anyone Help ???
riad
I have a Project scheduled on P6, I made WBS for Shopdrawing, Material sbumittal & Approval and Construction.
Then I add resourcs manpower to Construction (WBS) only.
when I start updating i noticed that Scheduled and Performance % complete roll up are showen for Construction (WBS) but for shopdrawing and material (WBS) remain Zero.
I tried to add Labor resource to S.D & M. (wbs) but still the problem is the same.
Can Anyone Help ???
riad
19 replies
Oldest firstLog in or join to reply