P3 to P6

Riyadh YahiaMember for 18 years 2 months
Created
3
1
0
Hi All,

I have converted P3 Schedule which the ( starting Date is 13 Mar 2006 & Finish Date 5 Feb 2009, Planned % was 74%) to P6 then I run F9 (Scheduling) Data date 21 Jun 2008 showing Schedule % Complete is 51%. So what is the reason behind the difference of % age, also I noticed that the remaining early start is 21 Jun 2008.

any can help solve this problem as i have to report to my compane soon.


Regards

riad

3 replies

Oldest first
  1. 0
    Paul Harris ·
    When you convert a schedule from one software package to another you are doing a data conversion not schedule conversion.

    All products have different algorithms and unless you are either lucky or have a very simple project schedule it is my experience that schedules will never calculate the same results in different products.

    Paul E Harris
    Eastwood Harris Pty Ltd, Melbourne, Australia
    Planning and Scheduling Training Manual & Book Publishers, Consulting and Training
    www.eh.com.au
  2. 0
    Riyadh Yahia ·
    Thanks to our respected auther for his interest in my subject,I got your Point, but how can I come over that problem????

    regards

    riad
  3. 0
    Paul Harris ·
    You have to manually adjust calculation options, durations, leads and lags etc until the schedules look the same.

    Paul E Harris
    Eastwood Harris Pty Ltd, Melbourne, Australia
    Planning and Scheduling Training Manual & Book Publishers, Consulting and Training
    www.eh.com.au