Performance % Compl vs. Schedule % Compl

John DrokovicMember for 17 years
Created
2
3
0
What is the difference between Performance % Complete vs. Schedule % Completete (in P6)?

2 replies

Oldest first
  1. 0
    Anu Tor ·
    The schedule % complete is calculated by (original duration - remaining duration)/original duration. For performance % complete is calculated by earn value / total value.
  2. 0
    Arnold Puy ·
    Hi John,


    The Performance % Complete is used to compute earned value and may be based on the Activity % Complete, and also specifies what percentage of the activity’s planned worth has been earned so far.


    The Schedule % Complete specifies how much of the activity’s baseline duration has been completed so far, and also indicates how much of the activity duration should be currently completed, relative to the baseline.

    Regards,

    Arnold