Activity with 1 day duration in P6
- Created
- 23
- 15
In my program, all activities with 1 day duration are consuming 10 hours.
I have checked all the durations in calenders, but all days are showing 8 hours a day. There is only one calender used throughout the project with 8 hours per day. But still all activities in program with 1 day duration consumes 10 hours.
Is it happening with me alone, or this is with everyone.
If yes, then plz does somebody has solution for this.
??????
:-|
23 replies
Oldest first- 0DWDieter Wambach ·Raviraj
This situation I never had. By the way: What is the default duration for new activities? (Admin --> Admin Preferences --> General: 10h?)
Did you add new activities by copy --> paste and by this you copied 10 hours as a duration?
If you’ll change to 1 day duration, what happens?
Regards
Dieter - 0OMOliver Melling ·As you know, P6 works in hours in the background, so if the ’1 day’ duration was entered when the admin preference was 10 it would consume 10 hours.
If your going to change it to 8, it won’t pass down the chain so to speak, you will have to go through each activity re-entering the duration of 1 day (which is now 8 hours). - 0ADA D ·Well, I found d solution (In fact, Dieter Wambach helped me out from d problem), but it’s very funny.
U can try by creating sample project on ur system of just 4-5 activities.
1. Set Admin preferences --> Default Duration as 10 hours per day.
2. Set user preference as 8 hours per day. (Just do it and Dont ask y?)
3. Set calender as 8 hours per day.
4. Set Duration for Activity 1 as 2 days. (it will consume 16 hours and NOT 20 hours as set in admin preference).
5. Set Duration for Activity 2 as 1 day. Now this will make u crazy. Say, activity started on Monday 8.00am, then it will finish on Tuesday 10.00am.
It will consume 10 hours because u have set that in Admin preference, even though u have entered duration in days.
Dont u think so, it shud take 20 hours for Activity 1, as set in Admin preference.
This is really crazy, as its a problem for activity with 1 day duration only.
OR am i confused??
Hope so, what i said is correct.
Plz reply. - 0DWDieter Wambach ·Raviraj
There might be a misunderstanding: Entry in Admin Preferences "Default Duration for new ..." means: If I just add a new activities and don’t manipulate the duration, it will have that duration indicated under the Admin Preferences. If I enter 1d for duration, the Admin Preferences "Time Units" will be used or - if different - my user preferences will be used.
Good luck!
Dieter - 0APAmit Parmar (PMP) ·
Hi Raviraj,in admin
Hi Raviraj,
in admin preference>Time periods please check if "use assigned calendarto specify the number of work hours for each time period" is checked ?
Cause if its not checked then Primavera would change the work hours acccording to the admin preferences Time Periods.
The problem in activity 2 must be coming because it is picking work hours from Time Periods and not Calendar assigned to it.
Regards
Amit Parmar
Check out my blog on Primavera at http://www.primaverablog.in. Do leave your comments :)
- 0ZRZahid Rehman ·
Hi Gents, Even I am years
Hi Gents,
Even I am years late on this platform but I am gald to get a solution of the above problem. few days back I was facing the same problem & I read all post regarding this but in vain. Finally one of my Kind net friend sent me solution which I am going to share with you guys....hope , it will work out for you guys,
1- Start of the Project to be at 1st working hour of the day,for example to be at 8.00am(from user preferences).2- Try to show the duration by decimal to detect the problem(from user preference).3- Adjust the data date hour to be at the end of the day or at the beginning of the day.4- Check the calendars working hours.5- The project finish date to be finished at the end of the working day.Hope the above will help you.Regards
Zahid Rehman
Log in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?