relationship links

Brian MittonMember for 18 years 7 months
Created
2
2
0
hello my fellow planners, I have just shifted from P3 to P6 and am finding it a bit strange but so far so good, but HELP PLEASE.
When I create a baseline from my current schedule, the relationship links are attached to the baseline and not to the current schedule. How can I get this right, please.

Thanks

Brian

2 replies

Oldest first
  1. 0
    Mark M ·
    Hi Brian

    I think you’ll find if you "move down" your baseline bar in the list of bars, your relationship lines should line up with the activities. The list of bars seems to be a hierarchy from top to bottom which effects how particular bars etc are displayed.

    Hope that helps

    Cheers
    Mark

  2. 0
    Brian Mitton ·
    Thanks Mark, owe you a pint.