MSP to P6

Jojit LazaritoMember for 21 years 2 months
Created
1
3
0
Hello Guys.. I have some very slight problem, as a plnner...

Is anyone here can share his/her opinion on how to transfer MSP Programme to P6, because it is almost 13000 task under MSP Programme that need to transmit to P6...

Please advice for me consume less time than to re-type it all again and asign individual logic....

Thanks in advance

1 reply

Oldest first
  1. 0
    Dieter Wambach ·
    Jojit
    First check the MSP project:
    - Calendars
    - Effort driven but intended to plan with fixed durations
    - User defined fields (no error of course)
    - ...
    Correct those errors first. Then create equivalent user defined fields in P6. Among the rules for import you can move any UDF of MSP to an UDF of P6.
    Check the rules for import - Help function!
    Good luck
    Dieter