Use of Reflections in P6.1

Beck LeeMember for 18 years 4 months
Created
0
3
0
Hi,

I have implemented P6.1 with the use of reflections for the Project Managers to update their reflections, before the Project Controls group checks these updates for quality and resource overallocations before merging these into the Source program.

This has it’s limitations;
- can’t use duplicate resource/role allocations
- doens’t merge some WBS name/code changes
- doesn’t like deleted or re-numbered activity ID’s
- merges project code changes without giving you the choice to do so...

Can anyone suggest a better way to do this?.. We would still like to maintain control of checking quality of schedule data before submitting to the "master program" which reports to management.

I suppose keeping a "what-if" copy for the PM’s to work on, then just check and replace at the data date cycle - is the simple solution - but has it’s own administrative implications..

Thanks!

Rebecca

Replies

Oldest first

No replies yet. Be the first to answer.

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?