Durations in Group Headings - P5
In the Open Standard
Ulkutan CimenMember for 25 years 4 months
- Created
- 5
- 3
0
When a number of activities are grouped, the group heading also calculates a duration, supposedly valid for all the grouped activities. Does anyone know how this is calculated or modified in P5?
I could not see any consistency in these durations, i.e. to which calendar they are based on. Even in groups consisting of 1 activity, the group heading duration is different than the activity duration.
I could not see any consistency in these durations, i.e. to which calendar they are based on. Even in groups consisting of 1 activity, the group heading duration is different than the activity duration.
5 replies