Remaining Units in P5

Yusuke KamuiMember for 18 years 5 months
Created
3
1
0
Hi,
Can someone please explain the difference between "Remaining Early Units" and "Remaining Late Units" ?

I am using one of them to calculate how many people I need per month given the Budgeted Units per month.


Thanks.

3 replies

Oldest first
  1. 0
    Anoon Iimos ·
    I believe it’s the same as remaining early works and remaining late works. Early and Late refers to time (with floats), while Units refers to resources and allocations (why not use average? i think it’s gross to fire workers on a monthly or weekly basis).
  2. 0
    Dieter Wambach ·
    Anoon
    Don’t try to throw unexperienced members, they have sufficient of uncertainity.

    Yusuke
    Early and late are expressions of cpm (Critical Path Method).
    For you as a scheduler it might be helpful to learn the basics. Have a look here:
    http://en.wikipedia.org/wiki/Critical_path_method
    and
    http://www.slideshare.net/dmdk12/the-network-diagram-and-critical-path
    Forward - and backward path lead to different positions of tasks within the timescale - as will do the planned assignments of resources.
    Good luck for planning!
    Dieter
  3. 0
    Anoon Iimos ·
    Hi Dieter,

    I don’t think Yusuke is inexperienced, and I’m just trying hard to give practical comments (hoping that it make sense). I really consider the question as vital " remaining early and late units" (thanks Yusuke).

    I believe the point is the actual number of resources that you are going to allocate considering the early and late data or figures (from your Plan) and the actual remaining works (is that right Yusuke?).

    cheers!