How to find Relationship ID

Ian MackrellMember for 18 years 3 months
Created
3
2
0
I am currently comparing programmes using Claim Digger and i am upto the relationship lags, however it only states the relationship ID number not the Activity ID. How do i find this id in the programme?

Cheers

Ian

3 replies

Oldest first
  1. 0
    Ian Mackrell ·
    In P5!!!!!
  2. 0
    Barrie Callender ·
    I don’t believe you can see the "Relationship ID" from Claim Digger displayed in P5.

    You need to go to the database and run a SQL query to get to it. It is the task_pred_id column in the taskpred table. It is unique in the database.
  3. 0
    Ian Mackrell ·
    Thanks Barrie,

    However, i cannot find the activity ID. I have run with the task_pred_id with the proj_id (shrt_name (filtered to the relevant project)), but for life of me cannot link it with the act_id (shrt_name) as it returns to null.

    I would be grateful if you knew how to get this.

    Cheers mate