P3 Target bars vs. P6 Baseline Bars

James BraghiniMember for 18 years 5 months
Created
6
5
0
I give up. How can I do the same thing in P6 like we did in P3 for comparing Target Bars? I have tried different ways but can never get the Secondary Bar to move seperatly from the Primary Bar in P6.

Any guideness would be appreciated.

James B.

6 replies

Oldest first
  1. 0
    Oliver Melling ·
    James,

    Check Project, Assign baselines and ensure you have the correct baseline assigned as the secondary one.

    Also, right click on the gantt, select bars and check that second baseline is ticked and the timescale is secondary baseline.
  2. 0
    James Braghini ·
    Oliver:

    I did that and still have the same problem. Does the filter used make a difference? Is there something that I am doing wrong when I update the baselines?

    James B.
  3. 0
    Carmen Arape ·
    James,

    In P6 you have Project assign and maintain baselines.

    Assign baseline: you assign the baseline that you would like to show.
    Maintain baseline: you CREATE the baselines.

    Before working with the bars that you want to display, you must assign the baseline.

    ONCE that you have selected the baseline bar, paying attention to the content of columns name and timescale you will get the filter.
    It is a predefined filter.

    HTH

    Cheers,
  4. 0
    Ali Farhat ·
    James,
    if your problem is NOT seeing the secondary baseline bar on the gantt chart.
    right click on gantt chart, bars..
    click on "second baseline", change the timescale to "secondary baseline" (it is not the default option)
    make sure each of the three bars (current, first and second baseline) do not coincide, that is having different rows.
  5. 0
    Kanishka Sauis ·

    Thank u Guys much appreciated

    Thank u Guys much appreciated :)

  6. 0
    Yasser Abouzeid ·

    engyasser1800@yahoo.com

    engyasser1800@yahoo.com

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?