Overhead Codes
In the Open Standard
Oliver MellingMember for 19 years 5 months
- Created
- 4
- 1
0
Does anyone know any workarounds to remove overhead codes from view within the timesheet/teamplay module of Primavera?
I have many codes that are no longer used and would like to remove them from view, but know if they are just deleted that the actual data is lost.
Is is possible to create an xl report of past data and just replace the OH codes periodically? i.e. capturing all historic data in access or xl and just using Teamplay to collate the hours?
I have many codes that are no longer used and would like to remove them from view, but know if they are just deleted that the actual data is lost.
Is is possible to create an xl report of past data and just replace the OH codes periodically? i.e. capturing all historic data in access or xl and just using Teamplay to collate the hours?
4 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?