P6: baseline TF display in column
In the Open Standard
John FrantzenMember for 21 years 9 months
- Created
- 3
- 2
0
During comparison reporting (layouts), one thing I like to do is list the "current" and baseline total float adjacent to one another (columns). This is easily done in P3... but when I’m setting-up layout columns in P6, I cannot find the baseline total float field. Can someone please point me in the right direction? Custom field? But how would I get BL TF into a custon field in the current project? I appreciate any and all insights. Thanks.