Claim Digger (Schedule Comparison Tool)

Milton MaindonaldMember for 19 years 4 months
Created
12
39
0
When I run the Claim Digger under the Tools Menu nothing seems to happen. Do I have to do something else prior?
(I’m wanting to identify deleted activities from the plan so they can be removed off our time clock system)

12 replies

Oldest first
  1. 0
    Ahmed Abu El Azm ·
    I have the same problem
  2. 0
    António Faria ·
    It seems like, but if you minimize Primavera or clicking in the "Show Desktop" you will see a new window (Claim Digger).

    Select the project that you want to compare, fields to compare and the kind of report.

    BR,
    AF
  3. 0
    James Braghini ·
    Make sure to check the string. We have the string correct but the folder was named something else.

    Good luck.

    James Braghini
  4. 0
    Patricia Le Clainche ·
    Hello,

    I had in the past the same problem and the solution was as describe by Antonio.

    I am not sure (I am not an expert in this matter), but I think it had been solved by a new Oracle version... you might explore this way.

    What is sure is that I do not have troubles any more.
    Good luck.
    Patricia
  5. 0
    Milton Maindonald ·
    Thanks you all for your reply’s but alas, I’m still not having any luck after trying your suggestions. I must have a more deep-seated computer problem.
  6. 0
    A D ·
    To run claim digger, u need to hav full access for following folder:

    C:\Program Files\Common Files\Primavera Common\Java

    If not, tell ur IT guys to have full access for above folder
  7. 0
    Ahmed Abu El Azm ·
    I have access - administrator rights - to this folder but what shall I do then?
  8. 0
    Milton Maindonald ·
    Have all those. I even downloaded the latest Java files from there web site. Still nothing.
  9. 0
    James Braghini ·
    Try giving yourself complete admin rights to the drive where the program is located (i.e. C drive. This includes security and read/wire permissions.

    Good luck,
    James B.
  10. 0
    Milton Maindonald ·
    I have hopefully found a fix for the problem in the Primavera KnowledgeBase. (Solution ID: prim42298)
    Our IT guy will be looking into the fix ASAP. I’ll let you know.
    Thanks again for you input.
  11. 0
    Milton Maindonald ·
    We’re all up and running.

    Very handy accessory!!!
  12. 0
    Mohamed Hegab ·

    Did you try an independent

    Did you try an independent tool such as schedule cracker (www.schedulecracker.com)?  It does the job with very nice reports and features.  They offer it for free 14 day full functional trial.