Durations VS Schedule

António FariaMember for 17 years 9 months
Created
2
2
0
Hello

I was preparing a time schedule and I notice the following when I scheduled (Tools\Schedule or "F9") the project: dispite the durations are differents, the activities had the finish date as having one day duration.
Example:
Activity Name Start End Duration
Earth Movements 01.02.2009 01.02.2009 2 days
Excavation 02.02.2009 02.02.2009 8 days

What I did:
1. inserted activity (insert button)
2. inserted durations (column Original Duration)
3. inserted relationships (bottom pane of the workspace)

What I notice:
Dispite Original Duration is OK, in the Bottom pane of the workspace, Remaining and At Complete duration was one day.

Example:
Duration--------------
Duration: 5 days
Actual: 0 days
Remaing: 1 days
At Complete: 1 days

When I corrected this in each activity, I scheduled and I got the correct finish date.

Is this normal? Insertion of data can only be done in the Bottom Pane of the Workspace? (at least to work correctly)

Thanks,
AF

2 replies

Oldest first
  1. 0
    Dieter Wambach ·
    António
    There is a project parameter "Link Budget and At Completion for not started activities":
    View Project --> select your project (must be open) --> Tab "Calculations" --> mark "Link..."
    Good luck!
    Dieter
  2. 0
    António Faria ·
    In the "mouche"! :)

    Thanks a lot. It worked. No luck was needed ;)

    I check other open projects and I notice the following:

    the 4 projects that I import to Primavera were without this option selected. New ones, Primavera has this option as default.

    One more time, thanks.
    AF