Calendar
In the Open Standard
António FariaMember for 17 years 9 months
- Created
- 2
- 1
0
One question as simple as this:
As default, my projects when created have Standard 5 days working days with basic holidays.
In one particular project, I was trying to change the calendar to Standard calendar.
What I did? Inside Project Workspace, I selected the project and changed the Activity Calendar field in the Bottom Pane/General. Primavera assumes this change, but when I’m in the Activity Workspace, activities still have old calendar. Even pressing "F9", activities don’t assume the Project Calendar Definition.
Best regards,
AF
As default, my projects when created have Standard 5 days working days with basic holidays.
In one particular project, I was trying to change the calendar to Standard calendar.
What I did? Inside Project Workspace, I selected the project and changed the Activity Calendar field in the Bottom Pane/General. Primavera assumes this change, but when I’m in the Activity Workspace, activities still have old calendar. Even pressing "F9", activities don’t assume the Project Calendar Definition.
Best regards,
AF
2 replies
Oldest firstLog in or join to reply