HELP P6 Calendar
In the Open Standard
Civ OczalevMember for 17 years 9 months
- Created
- 6
- 2
0
Someone is changing the calendars (from 7 days to 5 days). And it’s frustrating because all my floats are changing.
However since I am updatin my project, how do I avoid the changes in the calendar.
If i use "project" calendar, I need to change the calendar foe each activity, one by one. is this the case?
Please advise. Thanks.
However since I am updatin my project, how do I avoid the changes in the calendar.
If i use "project" calendar, I need to change the calendar foe each activity, one by one. is this the case?
Please advise. Thanks.
6 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?