XER P6 to P5

David HardingMember for 18 years 11 months
Created
4
2
0
Hi,

has anybody had any problems reading a XER file in Primavera P5.0 when it’s been created in Primavera P6.0?

A couple of our partners are reporting that their P5.0 software can’t read P6.0 XER’s. There is no option to create a version sensitive XER.

thanks

4 replies

Oldest first
  1. 0
    Arnold Puy ·
    Hi David,

    First of all, Welcome to PP.

    When it was created in P6 and open it in P5 then simply export the .xer file to Primavera Contractor P5.0-(XER).

    The other way around is to export using the Primavera PM/MM-(XER) ans save it.

    Then open the .xer file using notepad. Simply change the 6.0.0 into 5.0.0 and save.

    HTH.

    Arnold


  2. 0
    David Harding ·
    Thanks for your assistance Arnold.

    Dave
  3. 0
    Arnold Puy ·

    You are welcome David.

  4. 0
    Peter Nicol ·
    Upgrade to 6.2.... it allows for the export anyway (but yes you can just change the number at the top of the xer also.

    - Peter