P6, Many resources usage profile w/one limit line

Abeer MahmoudMember for 18 years 3 months
Created
5
2
0
I have 3 recources; R1, R2 & R3 with different limits,activities and resource usage profile.
Now it is required urgently from me to merge these recources to work as a one group and with one limit line to be shown in one resource usage profile how can I do this?????

Please help me in steps to follow

Thanks in advance,
Abeer

5 replies

Oldest first
  1. 0
    Dieter Wambach ·
    Abeer
    1. If you’ll want to keep the single assignments, just select all three resources. A common curve with an overall limit will be shown.
    2. You one resource with capacity of three: Create this new resource then by "replace by" (icon right border of the P6 window) move all assignments to this new resource. Then set the single res. to inactive.
    Good luck
    Dieter
  2. 0
    Abeer Mahmoud ·
    Dear Dieter,

    Thanks for your quick response and kindly note that I did the second alternative yesterday but I want to try alternative #1 but I don’t know how so; could you please gave me the steps to follow it.
    Regards,

    Abeer
  3. 0
    Dieter Wambach ·
    Abeer

    Very easy:
    1. Open Resource Usage Profile
    2. Push "Display..." within the lower left window the upper left corner. --> filter by --> Current Project’s Resources
    3. Select your three resources (using Ctrl key)
    4. In the lower right window you can see the histograms for all three with their overall limit.

    If you want to see the columns as stacked histograms --> Push "Display..." within the lower right window the upper left corner. --> Stacked histogram --> work according to the help function

    Good luck
    Dieter
  4. 0
    Abeer Mahmoud ·
    Thanks Dieter,

    I appreciate your help very much it worked and I am verrrrrrrrrry happppppppppppy.
    Thanks a lot

    Best Regards and happy day
    Abeer
  5. 0
    Muhmad Elshaikh ·

    Hi Abeer & Dieter Thanks for

    Hi Abeer & Dieter

    Thanks for you both, i have two comments:

    1. for point one it is only working for labor & nonlabor resources but not for materials

    2. for point two, Dieter in which interface can i find "replace by" icon, isearch on Project, resources and all i didn't find it, am using P6.7 right now

    Thanks in advance

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?