Updating the schedule with Expected finish
In the Open Standard
Carmen ArapeMember for 22 years 3 months
- Created
- 5
- 2
0
Dear ALL
Updating the schedule with Expected finish
While using P3, my favourite update method was : recording actual dates and remaining duration;
With P6, I have found a new method: recording actual and expected finish. AFTER updating two months with this method, I have found the following:
1.- For the first update, it was OK.
2.- Second update, I have found a lot of inconsistencies, wrong calculation on my new finish date.
Can anyone give me a clue regarding what it might happen? The use of expected finish is not reliable.
Cheers,
Updating the schedule with Expected finish
While using P3, my favourite update method was : recording actual dates and remaining duration;
With P6, I have found a new method: recording actual and expected finish. AFTER updating two months with this method, I have found the following:
1.- For the first update, it was OK.
2.- Second update, I have found a lot of inconsistencies, wrong calculation on my new finish date.
Can anyone give me a clue regarding what it might happen? The use of expected finish is not reliable.
Cheers,
5 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?