Skip to content

Finanical approval calendars

Nathan BurmanMember for 18 years 10 months
Created
2
5
0
I need to create a calendar for financial approval meetings and would like to start from a calendar with zero working days to allow specific work days representing dates the financial approval can take place.

I can do it the long way but wondered if anyone knew a way to force P6 to create a calenar with a standard work week of zero days?

I’ve tried and when you click ok on the work week with all the days set to 0 hours it return to the default hours.

2 replies

Oldest first
  1. 0
    Dieter Wambach ·
    Nathan

    As far as I know the lowest value is 1 day with 1 hour. Currently I have no idea for a good workaround.

    Regards
    Dieter
  2. 0
    Nathan Burman ·
    Thanks Dieter,

    I didn’t think it was possible besides having a 1 day week and setting most days to non work.

    I’ve actually done this the long way now but if anyone else has a faster way to do it I’d be interested to know.

    Regards,

    Nathan

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?