Baseline Issues in P6
In the Open Standard
Nancy RobertsMember for 17 years 9 months
- Created
- 1
- 3
0
Hi All,
Hopefully you have an answer to my question. I have approx 40 separate projects in P6 that are baselined; the current and baseline are the same since we have re baselined the projects. When I open a single project the baseline and current look and indeed are the same dates. When I open two projects it seems to me that the baselines intermingle. This is only happening on 5 of my projects. I can open them alone but when I open them together the baseline dates are reading from one baseline. I will say the names are the same but that shouldn’t matter since they all have unique WBSs.
Any help would be appreciated.
Thanks
Hopefully you have an answer to my question. I have approx 40 separate projects in P6 that are baselined; the current and baseline are the same since we have re baselined the projects. When I open a single project the baseline and current look and indeed are the same dates. When I open two projects it seems to me that the baselines intermingle. This is only happening on 5 of my projects. I can open them alone but when I open them together the baseline dates are reading from one baseline. I will say the names are the same but that shouldn’t matter since they all have unique WBSs.
Any help would be appreciated.
Thanks
1 reply
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?