Skip to content

Baseline Bar - P6.0

Xiaobao LeiMember for 17 years 7 months
Created
7
3
0
Hi Planners,

There is one headache problem in P6.0.

When there are some actual activities and I rebaseline the project, the rebaseline bars of those actual activities just shows their "Planned Dates", but not "Current Dates", in another word, the rebaseline bar is shorter then current bar even I’ve not done any updates.

This is not good to compare the progress.

In P3.1 there is no this problem.

Can anyone help on this? Appreciate!

7 replies

Oldest first
  1. 0
    Arnold Puy ·
    Hi Lei,

    Make sure that the bar you displayed is the baseline bar.


  2. 0
    Xiaobao Lei ·
    Thanks for comments, Arnold.

    Yes, it is baseline bar. The problem is that this baseline bar just links to its "Planned Date", but not the "current date" of its rebaseline date.
  3. 0
    Arnold Puy ·
  4. 0
    Arnold Puy ·
  5. 0
    Arnold Puy ·
    Lei,

    Sorry for the blank post. Because, my internet connection is having the problem!!!

    Try to go to Admin --> Admin Preferences, under the Earned Value tab, Earned value calculation: The Default is "Budgeted values with planned dates" try to change to "Budgeted values with current dates" and then close.

    Regards.



  6. 0
    Xiaobao Lei ·
    Hi Arnold, I should call you Mr. Expert.

    Yes,you are right. It is fixed. Appreciate!

    Regards,
  7. 0
    Arnold Puy ·
    Mr. Xiaobao Lei,

    Thank you so much for that. We are happy to help.

    Regards,

    Arnold

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?