Skip to content

adding contractor schedule to original one

Nasreen AlmutawaMember for 17 years 7 months
Created
1
1
0
When the project reaches construction phase, is it possible to add the schedule recieved from the contractor to the original project schedule and make it as one big schedule ? Can that be done ? we tried it but we are having issues with the S-Curve,since it will not match what can i do ?

1 reply

Oldest first
  1. 0
    Arnold Puy ·
    Hi Nasreen,

    Yes, it is possible. But first, make sure that you have a backup of both projects.

    Open the Two projects, the original project and the contractor schedule. Go to WBS workspace and copy or cut the WBS and paste to the original project.

    Be sure to mark all the checkbox of the "Copy WBS Options" & Copy Activity Options" and relate or link these activities to your original project.

    With regard to S-Curve, I think you need to double check the resources assigned to your activities. You can modify or change the quantity using excel sheet.

    HTH.

    Regards,

    Arnold

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?