Timesheet Actuals

Sue ChambersMember for 20 years 1 month
Created
5
3
0
I am trialing the Primavera timesheets and when we have processed them we apply the actuals to the plan but if we then schedule the system removes the actuals.
I need to keep the actuals from the timesheets and the ability to schedule.
Any ideas anyone on how to solve this?

5 replies

Oldest first
  1. 0
    Joao Ribeiro ·
    Just an idea: Have you tried to closeout the period?

    HTH
  2. 0
    Sue Chambers ·
    Thanks Joao
    What do you mean by close out the period?
    How do I close out the period?
  3. 0
    Joao Ribeiro ·
    Sorry, in P6 is called "Store period performance". Read carefully the manual/help before using in a live database.

    HTH
  4. 0
    Dieter Wambach ·
    Sue
    Did you check for "Autocompute actuals"?
  5. 0
    Sue Chambers ·
    Thank you Joao and Dieter I will try this.

    Sue