Timesheet Actuals
In the Open Standard
Sue ChambersMember for 20 years 1 month
- Created
- 5
- 3
0
I am trialing the Primavera timesheets and when we have processed them we apply the actuals to the plan but if we then schedule the system removes the actuals.
I need to keep the actuals from the timesheets and the ability to schedule.
Any ideas anyone on how to solve this?
I need to keep the actuals from the timesheets and the ability to schedule.
Any ideas anyone on how to solve this?