P6 Report Loading Error
In the Open Standard
Izam ZakariaMember for 20 years 4 months
- Created
- 4
- 1
0
Guys,
I’ve a problem currently which BQ was uploaded for quite example 10 000 mhrs. But the report just shown 1 000 mhrs (period totals)column only.Another 9 000 mhrs was allocated on (post) column.What the heck is this? I did on others project which used the same report group resource and the result is perfect. Guys pls help me
I’ve a problem currently which BQ was uploaded for quite example 10 000 mhrs. But the report just shown 1 000 mhrs (period totals)column only.Another 9 000 mhrs was allocated on (post) column.What the heck is this? I did on others project which used the same report group resource and the result is perfect. Guys pls help me