First Update P6 Schedule.
In the Open Standard
Shahzad AhmadMember for 18 years 8 months
- Created
- 10
- 2
0
Dear All
I need to confirm beofre making any mistake to update my Schedule.
i have made a simple Schedule without resource .
all activity are Task depant..
Activity type : fixed Duration & units.
Duration type is: duration.
i want to update based on my Physical % which is i am obtaing thro my progress mesurement sheet.
what i am going to do is i will tick Actual start date and putting physical % ... after that press F9 to see the result.
Do i need to change Duration type before update?
Do i need to change remaing duration while putting Physical % say 10%...
Please advise me in simple way to avoid confussion.
Thanks
Shahzad
I need to confirm beofre making any mistake to update my Schedule.
i have made a simple Schedule without resource .
all activity are Task depant..
Activity type : fixed Duration & units.
Duration type is: duration.
i want to update based on my Physical % which is i am obtaing thro my progress mesurement sheet.
what i am going to do is i will tick Actual start date and putting physical % ... after that press F9 to see the result.
Do i need to change Duration type before update?
Do i need to change remaing duration while putting Physical % say 10%...
Please advise me in simple way to avoid confussion.
Thanks
Shahzad
10 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?