PM6 Calculating Multi-projects total float problem
In the Open Standard
Zhang HaixiangMember for 21 years 6 months
- Created
- 19
- 11
0
Hi,
I have a problem, hope someone can help me
I have 2 project in PM6, they have same data date,calender...
activity1 in Project A, has a constraints - finish on or after.
activity2 in project B, has a constraints - as late as possible, it’s successor is activity1 FS+0
what i expect is after F9, activity2 will move and finish just before activity1 start.
then after F9 all the dates are correct,but the total float for activity2 is negative. i think it should be same as activity1.
can anyone explain how to solve the problem,thanks
I have a problem, hope someone can help me
I have 2 project in PM6, they have same data date,calender...
activity1 in Project A, has a constraints - finish on or after.
activity2 in project B, has a constraints - as late as possible, it’s successor is activity1 FS+0
what i expect is after F9, activity2 will move and finish just before activity1 start.
then after F9 all the dates are correct,but the total float for activity2 is negative. i think it should be same as activity1.
can anyone explain how to solve the problem,thanks
19 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?