P6, Invisible Bars

Abeer MahmoudMember for 18 years 3 months
Created
2
3
0
At P6, Kindly note that when I add new activities at under progress schedule and run schedule some of not started activities/remaining bars were invisible I wonder why and how can I solve this case?

Regards,
Abeer

2 replies

Oldest first
  1. 0
    Arnold Puy ·
    Hi Abeer,

    Try to check your Remaining Bar in View Menu --> Bars.

    Regards.
  2. 0
    Riyadh Yahia ·
    Hi Abeer,

    this problem face you when you insert an activity without assining it to the proper WBS.

    I mean you work on a part of the WBS you will not see it, but if you choose all you will see it.

    go to activity detail (then) General tab (then) WBS so check the proper WBS for that bar.

    i hope this will do.

    regards

    riyadh