P6.1 imported into P6

Shahzad AhmadMember for 18 years 8 months
Created
2
1
0
Hi All

I want import a files P6.1 in to P6 ,

error msg display P6.1 version could not imported in to P6.

how i can import P6.1 in to P6

Thanks
shahzad

2 replies

Oldest first
  1. 0
    Ferdinand U. ·
    this was solved already in other posts

    edit the xer file using notepad

    change the version 6.1.0 (or whatever higher version) located at the top left side to 6.0.0(or to your version).

    then save.

    now you can import it already.
  2. 0
    Shahzad Ahmad ·
    Hi Ferinand


    Thanks so much.

    Slamaat

    Reg.
    Shahzad