wrong budget units and calendar !!

Mimoune DjouallahMember for 20 years
Created
3
2
0
hi


i have imported an xer files produced by P5, i am using P6, i got activities durations,and wrong budget units ( labor an non labor),

but when imported to P3( using p3 format of course), every thing is correct, any idea what i am doing wrong on P6, any options should I use !


please help



3 replies

Oldest first
  1. 0
    Arnold Puy ·
    Hi Mimoune,

    Try to check the "Units Format" & "Durations Format" including "Hours per Time Periods’ in User Preferences --> Time Units.

    Regards,

    Arnold
  2. 0
    Mimoune Djouallah ·
    I checked, i have the same options as a coworker, it works for him not me


    me sad ;(
  3. 0
    Mimoune Djouallah ·
    sorry for the noise, it seems i changed some options in the import configurations.

    note to myself; never touch p6 default configuration option