Milestone dates are changing
In the Open Standard
Yusuke KamuiMember for 18 years 5 months
- Created
- 2
- 3
0
Hi, I’m using P6 and my question is, how come everytime I schedule my project those tasks whose Activity types are either "Start Milestone" or "Finish Milestone", the dates will change as per the data date I run the schedule?
How to fix it without using any constraint? Is constrint the only way to fix those milestone dates?
Thanks.
How to fix it without using any constraint? Is constrint the only way to fix those milestone dates?
Thanks.
2 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?