Switching PM5 PMDB database

Alexandre Faulx-BrioleMember for 23 years 8 months
Created
1
5
0
Hello planners,
to organize training sessions, I need to prepare a database on my PC and paste it to the trainees’ PCs
I cannot connect PM5 to the database after I have pasted MY database onto another PC, and moreover I can no longer connect to the original database on that PC
what did I miss?
Thank you for your help,
Alexandre

1 reply

Oldest first
  1. 0
    Joao Ribeiro ·
    Hello Alexandre, bon soir,

    First you must copy the DB into the new server’s data directory. Once the DB manager "sees" the DB, you must run two SQL scripts to restore privuser and pubuser. If you have access to Primavra’s Knowledge base or Primavera’s Admin Manual, the scripts are there under backup and restore DBs. If not, drop me an email (jcferreiathotmaildotcom).

    HTH

    P.S.: The answer will be provided only to Alexandre Faulx-Briole. All other requests will be ignored.