Skip to content

WBS

Rohit RangnekarMember for 17 years 4 months
Created
2
1
0
Dear All,



My project id is TEL1. Whenever I am going to create WBS , it expands in such away TEL1.1 , TEL1.2 . But I do not want this type of WBS and Wants like T1.A , T1.b. Is it possible in primavera to define characters for WBS ?


Regards,

2 replies

Oldest first
  1. 0
    Arnold Puy ·
    Hi Rohit,

    Unfortunately No. Because the WBS always start with the Project ID and followed by the WBS Code.

    The only way is to change your Project ID into T1 and input manually the WBS Code A,B.....C.

    Regards,

    Arnold
  2. 0
    Rohit Rangnekar ·
    Thanx sir

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?