multiple resources

Rohit RangnekarMember for 17 years 4 months
Created
1
1
0
Dear Sir,

If we want to assign 2nos. same resource to an activity , how can we do it?

Regards,

1 reply

Oldest first
  1. 0
    Arnold Puy ·
    Hi Rohit,

    Just simply add the same resource to your selected activities. But make sure that in the project setting, under project detail --> resources tab, tick the checkbox next to "Resources can be assigned to the same activity more than once".

    Regards,

    Arnold