Baseline
In the Open Standard
Rohit RangnekarMember for 17 years 4 months
- Created
- 0
- 3
0
Dear Sir,
Can anybody help me out by describing step by step procedure after maintaining primary baseline of planned project , if I want to update project progress after 15days ? Is updation done for activities progress only or there are other criterias also?
Regards,
Can anybody help me out by describing step by step procedure after maintaining primary baseline of planned project , if I want to update project progress after 15days ? Is updation done for activities progress only or there are other criterias also?
Regards,
Replies
Oldest firstNo replies yet. Be the first to answer.
Log in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?