how to do multi-level schedule?
In the Open Standard
Niles LuoMember for 20 years 10 months
- Created
- 3
- 4
0
Dear all,
In some case, we use multi-level schedule to control our project.It always confuses me that the relationship between higher level and lower level schedule,such as Level 3(L3) and Level 4(L4). For detail, I have 3 questions.
First, the WBS elements in L4 are the same as these in L3 or not?
Second, the activities in L3 schedule must be convert to the lowest WBS elements of L4 schedule?
Last one is the relationship of activities in L3 and L4 schedules. One in L3 must match one or many in L4,isn’t it? It is trus or not that one activity in L4 must match one in L3?
All of them have been puzzled me for a long time, please help me. thank you very much.
Regards
niles
In some case, we use multi-level schedule to control our project.It always confuses me that the relationship between higher level and lower level schedule,such as Level 3(L3) and Level 4(L4). For detail, I have 3 questions.
First, the WBS elements in L4 are the same as these in L3 or not?
Second, the activities in L3 schedule must be convert to the lowest WBS elements of L4 schedule?
Last one is the relationship of activities in L3 and L4 schedules. One in L3 must match one or many in L4,isn’t it? It is trus or not that one activity in L4 must match one in L3?
All of them have been puzzled me for a long time, please help me. thank you very much.
Regards
niles
3 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?