issue with the baseline
In the Open Standard
Prem Kumar,Member for 21 years 7 months
- Created
- 3
- 2
0
Hi all;
Can anybody tell me why, I updated a programme, and I didn’t created and assigned any base line. the assign baseline window has current project as the base line. but my start and finish for the current project activities are not matching with the baseline start and finish for the activities which are completed or in progress.
Can anybody tell me why, I updated a programme, and I didn’t created and assigned any base line. the assign baseline window has current project as the base line. but my start and finish for the current project activities are not matching with the baseline start and finish for the activities which are completed or in progress.
3 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?