issue with the baseline

Prem Kumar,Member for 21 years 7 months
Created
3
2
0
Hi all;
Can anybody tell me why, I updated a programme, and I didn’t created and assigned any base line. the assign baseline window has current project as the base line. but my start and finish for the current project activities are not matching with the baseline start and finish for the activities which are completed or in progress.

3 replies

Oldest first
  1. 0
    A D ·
    Hi Prem,

    P6 is correct in this situation. To differntiate between these dates, ADD these columns "Early Start", "Early Finish", "Start", "Finish", "Planned Start" and "Planned Finish".

    Early Date columns will give you the dates, based on the completed activities or in progress activities.

    Start & Finish Columns and Planned Dates will match, as you have not assigned any baseline.

    Now, when you will update the program and will assign the baseline, please make sure that baseline uses "Budgeted Values with Current Dates".

    This option you can find in Admin Preferences --> Earned Value Tab --> Earned Value Calculation

    Cheers,

    Ravi
  2. 0
    Prem Kumar, ·
    hi

    Thank you very much for your help

    regards

    prem
  3. 0
    A D ·
    Also, after assigning baseline, check dates in START and FINISH columns rather than early dates.