Milestone Placement by Schedule % Complete
In the Open Standard
Tory StregeMember for 19 years 6 months
- Created
- 5
- 6
0
I am creating a schedule of milestone activities that need to be placed on the schedule driven by percent of project complete.
I am setting this up as a WBS plug-in to be imported to projects. For example when a project reaches 70% completion certain notifications and closeout activities need to happen.
Does anyone know if P6 can accomidate this? Is it capible of placing milestone activities that are linked only to % of project complete? If so, how?
I am setting this up as a WBS plug-in to be imported to projects. For example when a project reaches 70% completion certain notifications and closeout activities need to happen.
Does anyone know if P6 can accomidate this? Is it capible of placing milestone activities that are linked only to % of project complete? If so, how?
5 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?