Predecessor type
In the Open Standard
Jason LIMember for 18 years 9 months
- Created
- 4
- 1
0
Hi planner,
I have a stupid question, an activity has a predecessor, relationship is FS, if the predecessor activity type is WBS summary or Level of effort. Then the activity will not drived by the predecessor. Can somebody kindly give me an explain. Thanks!
I have a stupid question, an activity has a predecessor, relationship is FS, if the predecessor activity type is WBS summary or Level of effort. Then the activity will not drived by the predecessor. Can somebody kindly give me an explain. Thanks!
4 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?