Please need help loading some resources
In the Open Standard
Mike MarkMember for 17 years 3 months
- Created
- 1
- 2
0
Which percent do i need to make active to show the progress on the actual unit column of the resources?
How can i spread manhour evenly on an activity after the activity has been progressed several time?
If the remaining duration on a resource is greater than the actual duration is the actual unit going to be zero and if so, why?
Please show me the step by step information on how to load manhour
in p6?
How can i spread manhour evenly on an activity after the activity has been progressed several time?
If the remaining duration on a resource is greater than the actual duration is the actual unit going to be zero and if so, why?
Please show me the step by step information on how to load manhour
in p6?
1 reply
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?