Need Information on resources

Mike MarkMember for 17 years 3 months
Created
1
2
0
how are budget ManHour’s spread?

Do they spread to the left of the data date?

How is remaining unit calculated?

How to compute actuals automatically?

1 reply

Oldest first
  1. 0
    Gary Whitehead ·
    budget manhours, when first assigned, are spread across the right of the data date -ie in the future.
    You choose how it is spread (evenly, front-loaded, etc) by selecting the appropriate resource curves

    How remaining units is calculated depends on the activity type (fixed units, fixed units/time, etc)

    There is an ’Auto Compute Actuals’ option you can set. This updates the programme automatically, assuming everything has happened precisely as planned. This of course, makes it entirely pointless -you may as well just get a copy of the baseline prrogramme and tip-ex over the date.

    All of this (apart from my rather jaundiced view of auto-update features) is in the e-manual that comes with the software -You’re probably best off reading that and having a play on a dummy project.

    Cheers,

    G