Labor Resources

Ruel CamaquinMember for 17 years 11 months
Created
3
1
0
If i have calculated the total Mandays for a particular scope of work, how can i calculate the no. of workers required per day?

This will be use for manpower resourcing in P6.

Thanks in advance...

3 replies

Oldest first
  1. 0
    Arnold Puy ·
    Hi Ruel,

    If the Total Man-days have already been allocated to your project then simply adjust your timescale into days and show the Resource Usage Profile. But make sure that your Unit of Time is in Day.

    You can as well, export your Man-days into Excel and calculate it there.

    Regards,

    Arnold
  2. 0
    Ruel Camaquin ·
    To further clarify,

    I have computed the Mandays to complete a particular scope, what i wanted to know is how will i get the no. of worker on a daily basis?

    Will i multiply or devide the production rate to 8 (on an 8 hrs daily sched)?

    Thanks.
  3. 0
    Muhammad Waseem, PMP ·
    Reul camaquin

    sir you just have to divide the mandays by total days that activity is taking to get no. of workers.

Log in or join to reply