to develope a schedule backforth

Bridget TangMember for 17 years 4 months
Created
2
2
0
Hello everyone,

I am working on a schedule that the completion date is fixed. Can I work out a schedule backforth? how? I already put the constraint on the completion date, but every activity still start from the data date automatically...


Thank all you guys so much!!!

Regards,
Bridget

2 replies

Oldest first
  1. 0
    Samer Zawaydeh ·
    Dear Bridget,

    You need to creat the activity list first, then you need to load the resources. If you want to start linking them backwards, that can be. Of course your activities must be all linked together.

    Once you created the schedule, if you are ahead of time, then you will have extra float, but if you are delayed then your activities will become critical.

    Best Regards,

    Samer
  2. 0
    Bridget Tang ·
    Dear Samer,

    Thanks for your reply.
    I guess I figured out what should I do.
    Because I always want to know how late my activities should start to make the project complete in certain day. I only need to refer to the late start/finish instead of early start/finish.

    It is easy to find the late bar in P3, I have to add a lat bar in P6. That is it.

    Thank you for your remind.

    Cheers,
    Bridget

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?