Hi.
I plan for a resource assignment like this : Jan (1000 hours) Feb (1000 hours) Mar (1000 hours).
On Jan I used only 800 hours. Primavera will spread the remaining hours (2200) evenly to Feb and Mar.
Can Primavera put remaining 200 hours from Jan to Feb (remaining unit of Feb will become 1200), not spread out to remaining duration like what it does now.
Thanks & regards
Khuong
I plan for a resource assignment like this : Jan (1000 hours) Feb (1000 hours) Mar (1000 hours).
On Jan I used only 800 hours. Primavera will spread the remaining hours (2200) evenly to Feb and Mar.
Can Primavera put remaining 200 hours from Jan to Feb (remaining unit of Feb will become 1200), not spread out to remaining duration like what it does now.
Thanks & regards
Khuong
8 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?